SAP Activate is an implementation framework used when implementing SAP cloud applications such as SAP SuccessFactors, and consists of a methodology, SAP Best Practices, and guided configuration content.
We recommend that all SAP SuccessFactors projects, including SAP SuccessFactors integration projects, follow the SAP Activate methodology.
The SAP Activate methodology uses SAP Best Practices for implementations and uses the agile methodology for quality control and rapid delivery. SAP Best Practices contains ready-to-use business process content and a reference cloud solution for a head start on implementations. SAP Best Practices are continuously updated so the latest improvements and functionalities are available. The guided configuration content provides the following benefits:
The SAP Activate methodology follows a four-phase project approach, as shown below: prepare, explore, realize, and deploy. The next section covers each phase in more detail. We’ll then discuss typical implementation timelines using the SAP Activate methodology.
This section explains the SAP Activate phases, the high-level activities within each phase, and the expected deliverables for an SAP SuccessFactors integration project.
In this phase, the project commences with plans and resources in place for delivery of the project.
The specific tasks associated with this phase include:
Before moving on the next phase, project stakeholders must agree that all required resources have been assigned, that the project schedule is complete, and that the project kickoff meeting has been conducted.
Once the project moves out of the preparation phase, the next phase is to review the solution in more detail and confirm that business requirements can be achieved within the project scope.
The specific tasks associated with this phase include:
The project is ready to move onto the realize phase once stakeholders agree to the business scenarios included in scope and that the solution meet your business requirements.
After the solution design has been confirmed in the previous phase, the realize phase goal is to build and test the configuration.
This phase includes the following tasks:
Note: Iteration 1 and 2 testing coincides with iterations 2 and 3 of the Employee Central project as the integrations require the foundation data to be built and fields defined.
The project is ready to move to the deploy phase when the stakeholders have signed off on the solution and agreed that the production cutover can proceed.
Once the integration systems have been built and tested, the deploy phase is where the configuration is moved to the production environment and where initial setup activities occur. At the end of this phase, the integration production system is fully operational.
The deploy phase includes the following activities:
The objective of this phase is met when all stakeholders agree that the cutover is complete, and the organization is ready to use and support the integration solution.
This section details the typical timelines for implementing standard integrations on an SAP SuccessFactors integration project.
Typically, a standard best practice Employee Central implementation project timeline varies between 12 and 20 weeks, as shown below, covering all phases of the SAP methodology. Standard Employee Central integrations will also be included as part of the project timeline, and critical integrations like third-party payroll and benefits will also be deployed at the same time Employee Central goes live in the production environment.
A typical standard best practices SAP SuccessFactors talent management implementation timeline varies per module, as shown here:
When implementing a new SAP solution, such as SAP SuccessFactors, project teams can utilize the SAP Activate methodology to follow best practices and set up solutions right the first time. This blog post explored the methodology as it relates to SAP SuccessFactors.
Want to learn more SAP Activate? Explore this Q&A with the authors of our SAP Activate book!
Learn more about agile project delivery from this free chapter excerpt.
Editor’s note: This post has been adapted from a section of the book Integrating SAP SuccessFactors by Donna Leong-Cohen, Vishnu Kandi, Rinky Karthik, and Seng-Ping Gan.